Schedule: Airness
April 12-16 Start SM Prep Week
April 12 Production Meeting #1
April 19 Production Meeting #2
April 19-May 5 Rehearsal
April 26 Production Meeting #3
May 2-5 Load-In
May 5 1st onstage rehearsal
May 6-8,10&11&12 Tech
May 11 & 12 Previews
May 13 2021 Opens
June 5 2021 Closing Date
June 6&7 Strike
June 9-12 Extension Week
June 13-14 Extension Strike
Schedule: Holmes and Watson
May 23 Build begins
June 7-11 Start SM Prep Week
June 14-July 6 Rehearsal
July 4-6 Load-In
July 6 1st onstage rehearsal
July 6 Crew Walk Through/Watch
July 6-10, 12 & 13 & 14 Tech
July 12-14 Previews
July 15 2021 Opens
Aug 21 Closing Date
Aug 22-23 Strike
Aug 25-28 EXT Performance
Aug 29-30 Strike EXT
April 12-16 Start SM Prep Week
April 12 Production Meeting #1
April 19 Production Meeting #2
April 19-May 5 Rehearsal
April 26 Production Meeting #3
May 2-5 Load-In
May 5 1st onstage rehearsal
May 6-8,10&11&12 Tech
May 11 & 12 Previews
May 13 2021 Opens
June 5 2021 Closing Date
June 6&7 Strike
June 9-12 Extension Week
June 13-14 Extension Strike
Schedule: Holmes and Watson
May 23 Build begins
June 7-11 Start SM Prep Week
June 14-July 6 Rehearsal
July 4-6 Load-In
July 6 1st onstage rehearsal
July 6 Crew Walk Through/Watch
July 6-10, 12 & 13 & 14 Tech
July 12-14 Previews
July 15 2021 Opens
Aug 21 Closing Date
Aug 22-23 Strike
Aug 25-28 EXT Performance
Aug 29-30 Strike EXT
Schedule: Airness
April 12-16 Start SM Prep Week
April 12 Production Meeting #1
April 19 Production Meeting #2
April 19-May 5 Rehearsal
April 26 Production Meeting #3
May 2-5 Load-In
May 5 1st onstage rehearsal
May 6-8,10&11&12 Tech
May 11 & 12 Previews
May 13 2021 Opens
June 5 2021 Closing Date
June 6&7 Strike
June 9-12 Extension Week
June 13-14 Extension Strike
Schedule: Holmes and Watson
May 23 Build begins
June 7-11 Start SM Prep Week
June 14-July 6 Rehearsal
July 4-6 Load-In
July 6 1st onstage rehearsal
July 6 Crew Walk Through/Watch
July 6-10, 12 & 13 & 14 Tech
July 12-14 Previews
July 15 2021 Opens
Aug 21 Closing Date
Aug 22-23 Strike
Aug 25-28 EXT Performance
Aug 29-30 Strike EXT
April 12-16 Start SM Prep Week
April 12 Production Meeting #1
April 19 Production Meeting #2
April 19-May 5 Rehearsal
April 26 Production Meeting #3
May 2-5 Load-In
May 5 1st onstage rehearsal
May 6-8,10&11&12 Tech
May 11 & 12 Previews
May 13 2021 Opens
June 5 2021 Closing Date
June 6&7 Strike
June 9-12 Extension Week
June 13-14 Extension Strike
Schedule: Holmes and Watson
May 23 Build begins
June 7-11 Start SM Prep Week
June 14-July 6 Rehearsal
July 4-6 Load-In
July 6 1st onstage rehearsal
July 6 Crew Walk Through/Watch
July 6-10, 12 & 13 & 14 Tech
July 12-14 Previews
July 15 2021 Opens
Aug 21 Closing Date
Aug 22-23 Strike
Aug 25-28 EXT Performance
Aug 29-30 Strike EXT
Teacher Substitute - Flexible Schedule
Tri-City United Schools -
Montgomery, MN
Personal Caregiver - Flexible Schedule
Senior Helpers - Burnsville -
Saint Paul, MN
Midwest metro with a flexible schedule
Curare Physician Recruiting -
Minneapolis, MN